Here you will find…
1 – APPLICATION REGISTRATION Register your application with the necessary information:
- Injection point coordinates.
- Planned production data.
We may require you to pay for the costs of preparing the connection estimate (maximum €3,000).
2 – ACCEPTANCE AND QUOTATION
Once your application has been accepted, we will send you a detailed quotation which you will be able to accept.
3 – NEDGIA CONTRACTING AND FIRST PAYMENT
We will formalise the contract and you will have to make the initial payment for the connection.
4 – PROJECT, PERMITS AND WORK
We will begin processing the project, formalities and work necessary to complete the connection.
5 – CONTRACTING, SUPPLY AND COMMISSIONING
Once the connection has been made, you will need to formalise the energy sale contract with the supply company of your choice (CNMC).
After commissioning, you must pay the remaining amount agreed in the contract.
Select an autonomous community:
- Accreditation of registration of the fuel gas plant in the Register of Industrial Safety Technical Installations of the corresponding Autonomous Community.
- Accreditation of registration of the low voltage installation in the Register of Technical Installations for Industrial Safety of the corresponding Autonomous Community.